Key reference points

  • Stop-drilling requires specific approved authorisation.
  • NDT may be required to establish the true crack end.
  • Hole geometry and follow-up actions come from current approved data.

Organised training notes

1Treat the crack as significant

Record the crack location and visible extent, protect the area and obtain the applicable approved inspection and repair instructions.

2Use stop-drilling only when authorised

The applicable SRM, repair drawing or engineering instruction must specifically permit the stop-drill action.

3Establish the true crack end

The visible end may not be the actual crack end. Use the specified NDT method and qualified personnel to establish the full extent.

4Protect the hole and structure

Location, final diameter, finishing, plug requirements and surrounding-surface protection must follow the approved procedure.

5Apply the required follow-up

Complete any repair, repetitive inspection, life limit and maintenance record required by the approved data.